How much concrete do I need?
Four steps: measure, turn everything into feet, multiply, and divide by 27 for cubic yards. Then add a little extra and count bags.
1. Measure in feet
Measure the length and width in feet. Thickness is usually in inches: divide it by 12 to get feet. 4 inches is 0.33 feet; 6 inches is 0.5 feet.
2. Multiply for cubic feet
Length × width × thickness gives cubic feet. A 12 × 10 foot patio, 4 inches thick: 12 × 10 × 0.333 = 40 cubic feet.
For a round column or post hole, use π × radius × radius × depth. A 10 inch hole is 0.83 feet across, so its radius is 0.42 feet.
3. Divide by 27 for cubic yards
A cubic yard is 3 × 3 × 3 = 27 cubic feet. 40 ÷ 27 = 1.48 cubic yards. Ready-mix trucks sell by the cubic yard.
4. Add extra
The National Ready Mixed Concrete Association suggests ordering 4 to 10 percent more than you measure. Forms bow, ground dips, and a slab 1/8 inch deeper than planned on a 4 inch pour already uses 3 percent more. 1.48 × 1.10 = 1.63 cubic yards.
5. Count the bags
Divide the cubic feet by what one bag makes and round up. With 10% extra the patio needs 44 cubic feet.
| Bag | Makes | Bags |
|---|---|---|
| 80 lb | 0.6 cu ft | 74 |
| 60 lb | 0.45 cu ft | 98 |
| 40 lb | 0.3 cu ft | 147 |
Yields are the ones printed on Quikrete and Sakrete concrete mix. Lightweight mixes make more per bag; check yours.